Today, the last solar modules were mounted, and we started with the wiring. There’s a total of 20 solar modules, divided up into 5 groups – i.e. four modules are connected in a row, and form a ‘string’, which are two cables individually connected to the DC/AC step-up converter. That’s a lot of wires, which had to be squeezed beneath roofing tiles, glass wool, and other obstacles.
-
« Home
Pages
-
Categories
-
Archives
- September 2019
- May 2018
- April 2018
- July 2017
- July 2015
- April 2015
- March 2015
- January 2015
- September 2014
- January 2014
- September 2013
- March 2013
- November 2012
- June 2012
- April 2012
- February 2012
- January 2012
- June 2011
- March 2011
- February 2011
- December 2010
- June 2010
- May 2010
- March 2010
- February 2010
- January 2010
- November 2009
- October 2009
- September 2009
- July 2009
- June 2009
- April 2009
- March 2009
- February 2009
- January 2009
- October 2008
- September 2008
- July 2008
- June 2008
- May 2008
- April 2008
- March 2008
- February 2008
- January 2008
- November 2007
- October 2007
- August 2007
- July 2007
- November 2006
- October 2006
- September 2006
- July 2006
- May 2006
- April 2006
- February 2006
- January 2006
- December 2005
- November 2005